Limonchito working document, published as-is. Prices and lead times are estimates from September 2026 and change often.

Lemon rev B: workshop production process (500 lemons) and prototype procedure

This covers a batch of 525 lemons (500 + 5 % scrap) and 263 cradles in a small NL workshop. - Mechanical reference: production/MECHANICAL_REVB.md, drawings/lemon_drawings.pdf (sheets 1–10; item numbers from sheet 8). - Board test: production/TEST_FIXTURES.md. - Electronics: production/ELECTRONICS_REVB.md.

Steps marked STOP are irreversible or gate the next station. Every station writes one line per unit (serial, operator, PASS/FAIL, reject code) into the production sheet.

Labour minutes are direct touch time per lemon. Machine and cure time is listed separately. Numbers are planning estimates; replace them with times measured on the first 20 units.

Workshop layout

 ┌──────────────── ventilated casting corner (extraction >= 300 m3/h, A2P3 respirators) ───────────────┐
 │  C1 scale + mixing   C2 vacuum chamber 19 L   C3 pressure pot 40 L (3.5 bar) + compressor           │
 │  C4 warm cabinet 35-40 C (moulds, post-cure rack)   C5 mould release booth   C6 silicone mould shelf │
 └───────────────────────────────────────────────▲─────────────────────────────────────────────────────┘
                                                 │ closed cores (S4)        │ cast lemons (S6)
 ┌──────────┐   ┌─────────────────────┐   ┌──────┴────────┐   ┌─────────────▼──────┐   ┌───────────────┐
 │ S0 goods │ → │ S1/S2 ESD bench:    │ → │ S4 core bench │   │ S6/S7 trim +       │ → │ S8/S9 final   │ → S11 pack
 │ in, IQC  │   │ hand solder, 2 test │   │ UV lamp, jigs │   │ inspection table   │   │ assy + test,  │   (+ S10 cradle
 │ shelves  │   │ fixtures            │   │               │   │ (daylight lamp)    │   │ Qi pads, LTE  │    bench)
 └──────────┘   └─────────────────────┘   └───────▲───────┘   └────────────────────┘   └───────────────┘
                                                  │
                        S3 print room: 2 SLA printers, wash + cure, support removal, insert press

Throughput plan (5 weeks, 2 operators)

Week Output
1 Setup, 20 first-article lemons through all stations, measure cycle times, make the 8 body moulds + 5 hatch moulds (6 h cure per half)
2–5 ~25–30 finished lemons/day
Station Labour min/lemon Machine / cure
S0 goods-in + IQC 0.3 –
S1 PCBA hand work 7.0 –
S2 board fixture test 3.0 4.5 min/board, 2 fixtures
S3 printed parts 2.0 ~90 SLA plates or outsourced cores
S4 core close 4.0 UV 2 × 60 s
S5 mould load + pour 1.5 2 h pressure cure
S6 demould + trim 2.0 24 h rack
S7 hatch skins 1.0 2 h
S8 final assembly 1.5 –
S9 final test + pairing 3.5 ~5 min, 4 in parallel
S10 cradle (1 per pair) 1.5 –
S11 pack 2.0 –
Total ≈ 29 min

S0 Goods-in and incoming inspection

S1 PCBA hand work (ESD bench)

  1. Break 2 carriers from the panel and deburr the edge.
  2. Put the PCB in the jig. Tack each carrier on its centre castellation, check it is square, then solder all 3 castellations per carrier. Carrier tilt ≤ 1° (jig gauge).
  3. Apply the domes with Snaptron tape, centred on the carrier pads.
  4. LRA: solder red → LRA_P and blue → LRA_N (sheet 10). Twist the leads and keep them under 20 mm. Put a foam pad on the LRA; it will sit at (−18.5, 0).
  5. Qi coil: solder the leads to QI_COIL1 / AC2, twisted, under 15 mm. The coil hangs below the board on its leads until S4.
  6. Punch the SIM to 4FF, insert it contacts down, close the hinged lid until it clicks.

S2 Board fixture test (TEST_FIXTURES.md)

S3 Printed parts (batch)

Part STL Material Per plate
Core top + bottom half stl_core_* Tough 2000 / Siraya Blu (or outsourced JLC3DP MJF PA12 / SLA 8001) 20 halves, on edge
Hatch plate stl_hatch_plate Clear resin 30
Plunger stl_squeeze_plunger Tough 2000 60
  1. Wash, cure and remove supports. Sand the parting faces flat on 400 grit on glass.
  2. Heat-press 2 ruthex M2x4 inserts into the core top-half bosses, flush to 0.1 mm below the ledge. Let them cool 10 s. STOP: a cracked boss means reject the half.
  3. MJF parts only: wipe the outside with thin UV resin and cure. This seals the porous surface for the film and the PU.

S4 Core close (sub-assembly for casting)

  1. Put the coil flat on the coil pad in the bottom half, ferrite up, leads toward −X. Hold it with a 0.1 mm PSA dot on the core (not on a cell; no cell is present).
  2. Lower the board onto the 4 seat ribs. The carriers drop into the lower halves of the windows.
  3. Put a plunger in each window from inside, flange against the wall, tip toward the dome.
  4. Run a bead of printing resin on the bottom-half parting face. Lower the top half onto it; the hold-down tab clamps the +X tip of the PCB. Cure with UV 60 s per side, then wipe the seam.
  5. Press a PET disc over each window from outside. Rub it down with the applicator and make sure the edge is sealed.
  6. Click test (STOP): press each plunger through the film with the spring probe. You must feel a click on each side at 4–6 N probe force, and the plunger must return. There is no power yet, so this is mechanical only.
  7. Fit the protective cap: a printed dummy hatch, which also keeps dust out.

S5 Mould load and pour (casting corner, batch of 4 moulds)

  1. Take the moulds from the warm cabinet (35 °C). Two thin release coats, flash 5 min.
  2. Leaf: brush 0.1 g of green-pigmented PU into each leaf recess of the bottom half. Leave it 3–4 min to gel.
  3. Remove the dummy hatch from 4 closed cores and put a hatch plug on each: 2 pins into the insert holes, plug seated on the hatch ledge.
  4. Lay each core+plug into the bottom half; the plug flange rests on the top face. Close the top half on the keys. Clamp plates on, bolts snug. Stand the mould on its +X edge.
  5. Mix 84 g (2 moulds) for 45 s, vacuum 60 s. Pour each runner mouth in 20–30 s, until PU shows in the vent. Top up.
  6. Into the pressure pot within 4 min of mixing, 3.5 bar, 35 °C, 2 h. Repeat for moulds 3–4 with a fresh mix.

S6 Demould, trim, inspect

  1. Depressurise and unclamp. Pull the plugs, open the mould, lift out the lemons.
  2. Cut the runner at the gate and the vent at the stem stub, flush to 0.2 mm.
  3. Trim the flash at the parting line and around the hatch opening.
  4. Inspect for voids > 0.3 mm in view, blocked dimples, seam flash > 0.2 mm, film wrinkle showing through, leaf fully green and bonded, stem stub complete.
  5. Rack for 24 h at room temperature before handling at S8. PT Flex 70 reaches full properties in 7 days, so allow 7 days before pack-out or drop testing.

S7 Hatch skins (casting corner, open moulds)

  1. Release coat. Pour 1.8 g PU into each cavity, textured face down.
  2. Press a clear hatch plate onto the 2 locating pins, skin side down, until the flange seats.
  3. Cure 2 h at 35 °C. Demould and trim the overflow at the seam edge. Punch the 2 screw counterbores clean.
  4. Stick the label (CE ≥ 5 mm, bin symbol, model "Lemon B", serial blank, address) on the underside. Stick the PORON 1.5 pad on the press ribs.

S8 Final assembly (cells enter here)

  1. Check the serial label on the lemon matches the batch sheet, and write the serial on the hatch label.
  2. Plug the cell into J2 (keyed; it latches). Lay the cell in the bay, label up, lead folded toward J2.
  3. Hook the +X tongue under the rim, lower the hatch, drive 2 screws to 0.10 Nm.
  4. Squeeze both sides: the click haptic confirms power.

S9 Final test and pairing

  1. Put the lemon on a Qi slot and run the final test in TEST_FIXTURES.md: - charge tick within 5 s, backend shows charging; - accelerometer pick-up event; - LED breath visible through the window; - both domes register only together; - pulse round-trip to the golden lemon within 25 s.
  2. Pair: assign partner IDs in the backend (A/B of one box). Send a pulse A→B and B→A.
  3. Charge state for shipping: 30–60 % (UN3481 / PostNL).

S10 Leaf cradle (263, one per pair)

  1. Press the puck into the pocket, logo down, cable toward the stem. The crush ribs centre it.
  2. Lay the cable in the underside channel and out through the stem groove.
  3. Put the foam spacer on the puck (stack to PUCK_H_MAX − puck height + 0.5). Fit the cover and 3 screws. Stick 4 feet on.
  4. Test with the golden lemon: charge tick within 5 s, no rattle, the lemon sits in the nest without rocking.

S11 Pack

  1. Box per pair: 2 lemons (30–60 % SoC), 1 cradle, manual card (includes the battery replacement instructions and the online URL, GPSR and CE text), insert.
  2. Outer carton labelled for UN3481 / SP188 where needed. Only 2 lemons with cells per PostNL parcel.

Appendix A: prototype procedure (one unit, R1/R2)

For the first 10–20 units, before moulds exist.

A1. Board 1. Bench bring-up on the nRF9151 DK and the 1NCE SIM as in rev A: attach, eDRX floor current on the PPK2 < 150 µA. 2. Board from JLCPCB. Do S1 by hand and S2 with a bench setup: DK as programmer, bench supply 3.9 V on TP8 via a 100 mA limit.

A2. Printed parts 1. Print one set: cores, hatch plate, 2 plungers, and 1 master stl_master_lemon_skin.stl, SLA 50 µm. 2. Sand the master to 600 grit, then acrylic coat + Inhibit X.

A3. One-cavity mould 1. Put the master in the parting board. Frame 4 walls × 1 cavity cut from stl_mould_box_frame.stl, or a cardboard/LEGO box. 2. Mold Star 30: half 1 (6 h), flip, half 2 (6 h).

A4. Core and fit checks 1. Do S4 by hand. 2. Dry-fit a cell (unplugged) and the hatch before casting: the cell lifts out, J2 is reachable, the rod sits over D1 (look through the clear plate), the hook engages. 3. Click check on both plungers.

A5. Cast and finish 1. Cast per S5 with a single mould. No pressure pot in R1 is acceptable, but expect bubbles in the dimples. Record the void count to justify the pot. 2. Cast the hatch skin in an open single-cavity mould. 3. S8 + S9 with a bench Qi pad and the backend.

A6. Measure and record - Trip force per side (target 12–20 N). - Skin thickness at the pads (cut sections of 1 scrap unit). - Qi charge current on 3 pucks. - LED visibility. - Drop test from 1 m onto carpet with the hatch closed. - Cell swap time for a first-time user (goal < 2 min).